This fast track programme was completed within an ambitious 16 week timeframe, with the first phase — the debating chamber and public meeting areas — delivered in just 10 weeks to meet the council’s operational deadlines.
To maintain momentum, decision-making was streamlined with on site coordination, and our teams worked continuously, including every weekend throughout the programme. One of the project’s key logistical achievements was the installation of a dedicated Air Handling Unit (AHU) for the debating chamber, lifted onto the roof during an overnight operation that required a full closure of the main road into Pontypridd.
The final phase — the remaining office floor — was completed four weeks after the initial handover, allowing full client occupation on schedule. The result is a modern, efficient, and future-ready office environment that supports the council’s public service delivery and operational needs.